Delaware Valley Water Reclamation Upgrade

Bucks County, Pennsylvania · 2023 · 6.2 MGD

Delaware Valley Water Reclamation Upgrade
Capacity
6.2 MGD
Scan setups
340
Tie-in conflicts
0
Duration
19 months

Capacity and nutrient-removal upgrade to a regional treatment plant that stayed fully in service throughout construction.

The problem

Forty years of undocumented modifications. The record drawings and the plant on the ground had drifted badly apart.

What we did

Terrestrial laser scanning of the entire process yard produced a point cloud that became the design base. Every tie-in was verified against measured reality before it was drawn.

Outcome

Zero field conflicts on process piping tie-ins, and no interruption to plant operations across a nineteen-month construction period.

Next project

Saint Anselm Academy STEM Wing

Continue

Start here

Tell us about the site.
We will tell you what it will carry.

Feasibility conversations are free and usually short. Bring an address and a rough idea of the programme.

Start a conversation